The planning application for the bypass was approved by the county council's regulatory committee on May 16 2007.
Land purchase orders were on display at the public exhibition at the Laverton in Westbury in June 2007.
Side Road Orders and Compulsory Purchase Orders were published on September 13 2007. The objection period for CPO was 3 weeks to October 8 2007, objection period for SRO was 6 weeks to October 29 2007. (On plans and maps page OR link to plans direct)
The scheme was “called-in” by the Secretary of State for Communities and Local Government following the Orders objection period a concurrent Public Inquiry was confirmed.
Following this a Rule 6 statement was submitted in September 2007 and Rule 7 statement submitted in January 2008.
A Public Inquiry will start on June 17 2008 and run for 24 days. A decision is expected in early 2009, and if the scheme is approved, construction work could start on the road during 2009. The bypass could then be open by 2010/11.
|